Al murad, Torre Road Leeds

 
We were commissioned by Al-Murad to design, supply, fabricate and install a three storey mezzanine floor inside an old cinema building. The building was already in use as a tile showroom and work was phased so that the store could maintain opening hours throughout the build. Access was a problem with all steelwork entering the building through an existing personell door and erection being carried out inside using a spider crane and spider access platform. Long span beams provide a large open plan area ideal for flexible use of the building, allowing it to be easily remodelled with various displays. Floor were both beam and block construction on shelf angles and at higher levels cold rolled purlins. We also supplied and installed six staircases of various designs, including all balustrades and glass panels where required.